The Construction Source
APRIL 2020 The concrete sawing and drilling work on the project took place in several phases over a three-year period. By the end, 20 million pounds were cut and removed above and below water, 5,000 holes were cored to depths up to 12 metres, and 697 square metres of surface was scarified. WCC was awarded the project in January of 2015. According to Brian, they earned that project due to their professionalism and reliability. The client initially awarded the project to a US firm that fell behind schedule on the first phase of the project. WCC was then awarded the second and third phases of the project, finishing both ahead of schedule. “We got a crack at it, and we showed them what we could do, and then we were in,” Brian says.
Made with FlippingBook
RkJQdWJsaXNoZXIy OTYzNTg=